Technology
Israel Accelerates Data‑Centre Build‑Out to Strengthen AI and Military Capabilities

Israel is expediting the construction of data centres to boost its data‑processing capacity, military strength and global influence. Prime Minister Benjamin Netanyahu announced a national plan in June to accelerate AI development, stating that Israel would become a global AI superpower. The government has removed regulatory bottlenecks and classified AI data centres as national infrastructure to bypass local regulation. A key project is the Ofek Data Centre, slated to be Israel’s largest data‑processing facility, with construction expected to finish in the second half of 2029 north of Ashdod. The $1.5 billion initial project, financed by a consortium that includes Serverfarm and the Israel Infrastructure Fund, will connect directly to European markets via an underwater fibre‑optic cable and integrate Nvidia GPUs. It will launch with a 130 MW capacity and expand to 200 MW. Israel currently has 67 data centres, and the government has capped new data‑centre capacity at 200 MW due to high grid demand. Electricity availability is a major operating cost for modern data centres. Minister of Energy and Infrastructure Eli Cohen has said Israel must develop nuclear energy and use natural gas from offshore fields such as Tamar, Leviathan, Karish and the upcoming Katlan to power the Ofek facility, which will be supplied by an 850 MW gas‑fired power station near Ashdod’s port. Analysts say domestic data centres are a strategic asset that can give a country bargaining power over those that rely on foreign infrastructure. They also provide faster and more stable inference for local businesses, the grid and military use. Israel has used AI in its military operations in Gaza and the West Bank. Europe lags behind in building data centres due to power grid bottlenecks, slow permitting and public opposition, and is increasingly dependent on data centres outside the EU. The United States hosts about 51 percent of the world’s data centres. Keeping servers within EU borders allows sensitive data to remain under European privacy laws and prevents foreign surveillance. The expansion of Israel’s data‑centre footprint is seen as a geopolitical move to secure a foothold in the next industrial phase of AI.
Frequently asked questions
What is the Ofek Data Centre and its planned capacity?
The Ofek Data Centre is Israel’s largest data‑processing facility, slated to finish construction in the second half of 2029 north of Ashdod. It will launch with a 130 MW capacity and expand to 200 MW.
How will Israel power the Ofek facility?
The Ofek facility will be supplied by an 850 MW gas‑fired power station near Ashdod’s port, using natural gas from offshore fields such as Tamar, Leviathan, Karish and Katlan. Minister Eli Cohen said Israel must also develop nuclear energy.
What is the government’s plan regarding new data‑centre capacity?
The government has capped new data‑centre capacity at 200 MW due to high grid demand, and Israel currently operates 67 data centres.