Kaiga Unit‑1 Reaches Criticality Again After 25 Years of Service

By

Kaiga Unit‑1 Reaches Criticality Again After 25 Years of Service

Kaiga Generating Station Unit‑1 (KGS‑1) in Karnataka reached criticality early Sunday, marking its second time achieving a self‑sustaining, controlled nuclear fission chain reaction after 25 years of operation. The Nuclear Power Corporation of India Limited (NPCIL) announced the milestone, noting that KGS‑1 had first attained criticality on 26 September 2000 and had supplied 37,670 million units before being shut down for refurbishment in April last year. The unit previously set a world record for 962 consecutive days of operation on 31 December 2018, achieving a 99.3% plant load factor and surpassing the former record of 940 days held by Heysham II (Unit 8/Reactor 2) in the UK. NPCIL highlighted that KGS‑1 reached criticality within 600 days of its shutdown for major refurbishment activities—en‑masse coolant channel replacement (EMCCR) and en‑masse feeder replacement (EMFR)—on 1 April 2025, making it the first NPCIL reactor to do so in such a short period. The Kaiga site operates four nuclear units totaling 880 MW and is constructing Units 5 and 6, which will add 1,400 MW and bring the planned capacity to 2,280 MW across six units. Units 5 and 6 are indigenous 700 MW pressurized heavy‑water reactors (PHWRs) with advanced safety features and are among the safest in the world. Three other PHWRs—KAPS‑3 & 4 and RAPP‑7—are already operating in Gujarat and Rajasthan. Components and equipment for the new units are supplied by domestic industry partners, and construction is carried out by Indian contractors in line with the Atmanirbhar initiative. Earlier, the Atomic Energy Regulatory Board (AERB) had granted permission for the first approach to criticality of Rajasthan Atomic Power Project Unit‑8 (RAPP‑8) at Rawatbhata after satisfactory safety reviews.

Frequently asked questions

When did Kaiga Unit‑1 first reach criticality?

26 September 2000.

How many consecutive days did KGS‑1 operate before setting a world record?

962 consecutive days.

How long did it take KGS‑1 to reach criticality after its shutdown for refurbishment?

600 days.