Bengaluru’s 2.5km Ejipura Flyover Still Unfinished After Nine Years of Delays

By

Bengaluru’s 2.5km Ejipura Flyover Still Unfinished After Nine Years of Delays

Bengaluru’s 2.5‑kilometre Ejipura flyover, nicknamed the city’s ‘Stonehenge’ for its long‑stalled construction, is unlikely to be completed by the end of December, extending the wait for commuters on the Koramangala‑Ejipura‑Madiwala corridor. The project, which began nearly nine years ago, was originally slated for completion in November 2019 but has faced repeated extensions, contractor failures, failed tenders, land‑acquisition issues, delayed clearances and payment disputes.

The flyover was first awarded to Kolkata‑based Simplex Infrastructure Ltd in 2017 with an estimated cost of Rs 158 crore. BBMP issued the work order on 4 May 2017 and set a November 2019 deadline. Construction was hampered from the start by delays in traffic police clearances, controlled‑blasting permission and land acquisition. By 2020 BBMP still struggled to acquire land, including property belonging to St John’s Hospital, the Central Public Works Department and the Indian Institute of Astrophysics. The Covid‑19 pandemic further disrupted labour mobilisation. Simplex, facing financial difficulties, failed to complete the project and construction ground to a halt. A public interest litigation in 2021 brought the matter before the Karnataka High Court. After judicial intervention, BBMP terminated Simplex’s contract in March 2022. By that time the civic body had spent about Rs 75 crore, forfeited Simplex’s security deposit of Rs 10.16 crore and imposed a penalty of roughly Rs 2.5 crore.

Finding a replacement contractor proved equally difficult. BBMP floated a fresh tender in August 2022, but the process was recalled. A January 2023 tender for Rs 144 crore attracted only one bidder, Hyderabad‑based BSCPL Infrastructure Ltd, which quoted about Rs 205 crore—about 44% above the estimate—leading BBMP to cancel the tender in February 2023. After revising estimates and adding a price‑adjustment clause, BBMP awarded the remaining work to BSCPL in November 2023 with a 15‑month completion deadline. The cost to finish the project was pegged at Rs 176.1 crore, excluding GST. The contractor cited delays in land acquisition, mobilisation payments and access to the casting yard, and required an Indian Institute of Science assessment of the structure built by Simplex. The assessment was completed in May 2024, several months after BSCPL took over. BBMP issued notices to BSCPL over slow progress and imposed a penalty of Rs 25 lakh.

In 2025 construction picked up, but land acquisition near St John’s Medical College Hospital continued to affect ramp construction. The project also faced objections from residents over BBMP’s proposal to remove 157 trees along Koramangala’s 100 Feet Road. More than 150 objections and suggestions were received before the public‑submission deadline in January 2025. Residents suggested changes to ramp design and alignment to preserve trees, while activists questioned the changing number of trees proposed for removal.

In January 2026, GBA chief commissioner M Maheshwar Rao directed officials to mark the land required at St John’s Hospital and begin construction of five portal piers. Hospital management agreed to allow temporary use of a portion of its land along the compound wall, with officials instructed to install barricades and rebuild the compound wall after construction. The administration announced fresh completion targets, but the project continued to miss them.

The flyover’s completion targets have shifted from November 2019 to 2020, December 2021, 2025 and multiple dates in 2026. The main elevated corridor still requires finishing work, including ramps, pavement, crash barriers, drainage, lighting, lane markings and road signage. Additional entry and exit ramps toward Sarjapur Road also need further land acquisition and may take longer to complete. For commuters, the concern is no longer just when the flyover will be inaugurated, but whether the entire project will finally be completed after years of disruption. A social media user summed up the frustration: “GTA 6 is getting released yet Ejipura flyover couldn’t get operational yet.”

Frequently asked questions

When was the Ejipura flyover originally scheduled for completion?

November 2019.

Which company was first awarded the contract for the Ejipura flyover?

Simplex Infrastructure Ltd.

What is the estimated cost of the Ejipura flyover under the latest contract?

Rs 176.1 crore, excluding GST.